The Digital Railway – Still On Time?

Standard

Back in the 1990s, Railtrack, and subsequently Network Rail, was charged with implementing the Europe wide signalling and train control system – ERTMS. This included the emerging ETCS (Electronic Train Control System), which was intended to remove the use of optical, lineside signals completely, and use track to train communications through a system of track mounted transmitters/receivers.

But is there more to this digital railway business than simply providing a better train control, management and signalling system?

The UK is still years behind our European neighbours in implementing the ERTMS platforms – although to be fair Railtrack/Network Rail have rolled out the halfway house of Train Protection & Warning System (TPWS), and today the core routes are at the entry level for ETCS. Today’s push for the “Digital Railway” has a lot of chatter, and media speak around improving performance and capacity for economic and commercial growth, but on the technology front, there seems to be some way to go – still.

Back in the late 1990s, the TPWS platform was supposed to have a 15-year lifespan, so is now beyond its final years of scheduled life, alongside the upgraded conventional signalling systems. By 2001 we were implementing systems that conformed to ETCS Level 3, with the Alstom TCS (Train Control System), for the upgrade of the West Coast Main Line (WCML).

There were plans to fit ETCS cab equipment in new stock, but following revisions to Control Period 5 with the ‘Hendy Review’ funding was cut, and the delays in deploying the system could be said to be pushing the UK further behind.

In 2015, the Rail Delivery Group published its 3rd annual “Long Term Passenger Rolling Stock Strategy”, where it stated that:

“During CP5 and CP6, the European Train Control System (ETCS) will be fitted to many fleets
 in preparation for the operation of the European Rail Traffic Management System (ERTMS).”

2015 Rolling Stock StrategyScreenshot 2019-11-21 at 10.51.37

Originally, it was considered that the modular nature of ETCS would be attractive to introduce the technology at Level 1 on secondary routes, interfacing to the existing IECC (Integrated Electronic Control Centres providing automated route setting, amongst other functions), and SSI (Solid State Interlocking) technology. This ability to upgrade in a phased manner was and is important to the UK and other rail networks, with open communications interfaces allowing integrated working across Europe.

But has the signalling and train control system finally been implemented to the optimistic plans of 2001, when the WCML upgrade was completed?

Perhaps not, since back in 2010, the Department for Transport (DfT)was working with outside advisers to try and determine the risks and benefits of adopting – at a future date – possible adoption of the European Railway Traffic Management System (ERTMS/ETCS) Level 3. This report came to the obvious conclusion that it was necessary, desirable, cost effective and efficient – but that was almost a decade ago.

Towards the end of 2016, and although the Rail Delivery Group, and Network Rail’s initiative for a cross-industry Digital Railway programme was progressing, the Transport Committee in its 7th Report (Rail technology: signalling and traffic management) showed that there was still much discussion on the topic:

Their conclusion:

We conclude that improvements to signalling and traffic management technology are needed to deliver a world-class rail network in the UK. In principle we support the idea that the deployment of the European Train Control System (ETCS), Traffic Management software and Driver Advisory systems should be accelerated but this should be subject to careful consideration of the Digital Railway business case, clarity about funding, and a clear understanding of how this programme would affect existing plans for work on enhancements and renewals. In particular, Network Rail’s Digital Railway business case should include a full cost/benefit analysis of all potential systems for a particular route, and consult upon it, before finalising its Digital Railway strategy. 

So, the UK’s rail network, its technology and industry does still appear to have some way to go – despite the fitting of ETCS Level 3 technology to the latest rolling stock, and plans for trials on various routes.

That said, the limited trials using Class 155 multiple units and departmental Class 37 diesels in Wales, on the Cambrian line paved the way for the application of ETCS level 2 on the Thameslink route, with GTR Class 700 trains. The trains began operating in August 2016, with a train running from St Pancras to Blackfriars, and having the ATO software overlay installed to allow automated operations. According to some reports this meant the driver would be responsible for supervising operations via instructions and guidance from in-cab screens, as opposed to controlling the train in a more conventional manner.

Currently, under the Control Period (CP) plans for the East Coast and ex-GWR main lines, ETCS will be introduced in phases – but it will take between 2024 and 2049 to complete the work. This is what is on the current plans:

  • CP6 (by 2024) – KX to Crews Hill and Hatfield
  • CP7 (by 2029) – Sandy to Peterborough; Grantham to Retford and Plymouth to Totnes
  • CP8 (by 2034) – Peterborough to Grantham; York (North) to Northallerton; Ferryhill to Alnmouth, and Paddington to Slough and Heathrow; Totnes to Exeter
  • CP9 (by 2039) – Retford to York (North); Northallerton to Ferryhill; Alnmouth to Berwick, along with Wootton Bassett to Exeter via Bristol, and Pewsey to Cogload Junction
  • CP10 (by 2044) – Didcot area (Cholsey to Wantage Road); Didcot to Oxford and Honeybourne
  • CP11 (by 2049) – Reading area (Slough to Cholsey); Wantage Road to Wootton Bassett; Reading to Pewsey

But no work will be undertaken on the ECML for Control Periods 10 and 11 – well at least that’s the current position, I think.

Thameslink trains now operate with ETCS Level2, with ATO in the central section, which puts that route at the forefront of implementing ATO with ERTMS, operating the new Class 700 Siemens “Desiro City” multiple units. These were procured under a PFI arrangement from 2013, from a consortium of Cross London Trains Ltd, which included Siemens Project Ventures GmbH, Innisfree Ltd., and 3i Infrastructure Ltd., and the trains began operating in 2016.  They were either 8 or 12-car units, and were later supplemented with an order for another 25 6-car trains – the Class 717 units, that would be used on the Great Northern line. In the end these new trains replaced no fewer than 6 older designs, from the Class 319 to Class 466.

Currently the only other ETCS Level 2 equipped and – well almost operational – trains are the Class 345 9-car trains for the Crossrail line. These actually began running in June 2017, and used at the outer ends, on the Great Eastern and Great Western main lines, as ETCS implementation is completed. In the Crossrail case, the trains are based on Bombardier’s “Aventra” design, but, unlike Thameslink, they are equipped for 25kV a.c. operation only, with no 3rd rail contact shoe. The Crossrail trains also carry equipment that allow them to use the TPWS warning system devised as a ‘halfway house’ towards ETCS in the 1990s.

Back in 2018, the DfT produced an 8-page implementation plan/technical spec for interoperability – the Control, Command System (CCS), under the slogan “Moving Britain Ahead”. On Page 4 of that document it states that the “Class B System”, which is the old “Halfway House” platform of TPWS from the late 1990s is supported by an industry wide spec. It also states that migration to ETCS will be on a “business led” basis, and implies that the “Class B System” will continue to be used in the UK.

“This specification defines all the required functionality and performance in a way which does not constrain the market to any particular supplier.” 


When ETCS was being promoted in the late 1990s/early 2000s, and when it was to be rolled out on the West Coast Main Line, in a phased manner, there were still multiple suppliers of ETCS equipment – whether for Level 1, 2 or 3. Not sure that still holds, but certainly the technology has progressed – perhaps the primary objection to speeding up its rollout is the rolling stock problem, and retrofitting to the large fleet of older vehicles. It’s great that it has been implemented for Thameslink, and there are still plans to implement – but TPWS was only intended to have a 15 year lifespan in 1999.

Following a review in 1999 of Railtrack’s West Coast upgrade, the approach to implementing train control through an ETCS platform was not progressed in the original manner, and it was recommended a more piecemeal approach, as an overlay to existing systems was taken. That is one of the ways in which ETCS can be implemented, with no need for a ‘big bang’ approach, and all that that would involve both technically, operationally, and S&T and driver training.

So, you might say, the UK’s “Digital Railway” is getting there, to misquote an old British Rail advertising slogan – but it will be sometime yet, before that objective is realised. In truth, some of us may not even be here to see that…… ah well.

-oOo-

TPWS

TPWS Feature coverClick on the image opposite, which will take you to a short feature written in 2001 about the implementation of TPWS – the UK’s initial step towards a full ERTMS/ATP train control system.

 

 

More Useful Links:

 

 

 

Electrification 1970s v 21st Century

Standard

Back in 1974, British Rail completed a major electrification between Crewe and Glasgow, and introduced a new timetable on 6th May that year.  This project was planned back in the mid 1950s, with the modernisation plan, which also included both the West and  East Coast routes.  Until 1966, when the London Euston to Manchester and Liverpool was completed, cash strapped BR was forced to delay the East Coast route, but in only 8 years the remaining length of the West Coast was completed.

BR Elec News 1974Today – or rather back in 2013 – work began on electrifying the railway between London Paddington and Cardiff, and planned for completion by 2018, a distance of just 145 miles, and now it has been put back to 2024.  The decision to electrify the line was taken in 2009 by the Dept for Transport, but it was beset with management/organisational problems almost from the word go, and the National Audit Office made some critical observations. Some of these were directed at Network Rail, but equally at the DfT, inckuding this little observation in its 2016 reportModernising the Great Western Railway“:

“The Department did not produce a business case bringing together all the elements of what became the Great Western Route Modernisation industry programme until March 2015. This was more than two years after ordering the trains and over a year after Network Rail began work to electrify the route.”

Comparing what was achieved in 1974, with the electrification work of major trunk routes like Glasgow to Preston and Crewe, to connect with the existing WCML wires, the time to complete this quite short route seems excessive.   The cost so far is over £5 billion, and whilst some of that is infrastructure, some includes of course the new ‘bi-mode’ trains.

Headspan Catenary Crewe to Carlisle 1973British Rail electrified 200 miles from Weaver Junction to Gretna, and Glasgow Central in just 8 years.  But it wasn’t just electrification back then, since there was considerable rebuilding and remodelling of trackwork, raising or replacing bridges, and resignalling throughout from London to Glasgow.  The overall cost was £74 million in 1970s prices, or approximately £1 billion today.

Another publication from BR at the time was “Electric All The Way”, which included these interesting comments relating to service improvements to and from Preston:

“The new pattern of services between London and Glasgow introduced on May 6 1974, provides passengers travelling to and from stations between Carlisle and Warrington on the newly electrified portion of the Anglo-Scottish route with more high-speed trains. Preston-Glasgow services have more than doubled, from seven to 15 daily, with an average reduction in journey time of almost one hour.  Preston-London trains have been increasedfrom 12 to 19.”

“Faster journey times and improved connections at Oxenholme for Windermere make the Lake District more easily accessible from all centres on the electrified route.”

So how many high-speed trains from Preston to Glasgow today, and how many southbound?

The introduction of the “Electric Scots” also saw the arrival of Britain’s most powerful AC electric locomotives – the Class 87.  Built by BREL workshops, and powered by GEC Traction equipment.

Class 87 at Preston copy

Class 87 at Preston in original 1970s livery

RPBRLY-8 copy

Out of use at Crewe, Class 87 in final BR livery

10 years later work began on electrifying the East Coast Main Line from Kings Cross to Edinburgh, which was completed in 1992, also completed in 8 years – clearly building on the experience and skills gained on the West Coast.  Some sections of the East Coast route were actually completed 12 months earlier than planned – London Kings Cross to Leeds for example.

Here again, the ECML saw the introduction of a nother new form of high-speed motive power, this time from the GEC Traction stable, and codenamed “Electra”, the Class 91 marked perhaps the zenith of British electric traction design.

gec076 copyWhy can’t we organise this as effectively today as happened in the 1970s and 1980s?  

Interesting Reads:

 

 

 

Digital rail revolution will reduce overcrowding and cut delays

Standard
Today, the current Transport Minister Chris Grayling said that as a result of the “digital rail revolution”:
Trains will become faster, more frequent, more punctual and safer through the introduction of new digital technology on the rail network.
Really?
And he went on to say:
“Transport Secretary Chris Grayling and Network Rail Chief Executive Mark Carne will today (10 May 2018) launch Network Rail’s Digital Railway Strategy and commit to ensuring all new trains and signalling are digital or digital ready from 2019. They will also set out that they want to see digital rail technology benefiting passengers across the network over the next decade.”
There is an interesting phrase in the statement above:  “… digital or digital ready from 2019….”  That sounds a bit like a supermarket sale … you know the one:  “… prices start from ??? …”  And you can rarely find the lowest price item.
The DfT’s statement went on to say:

New digital rail technology will:

  • safely allow more trains to run per hour by running trains closer together
  • allow more frequent services and more seats
  • cut delays by allowing trains to get moving more rapidly after disruption
  • enable vastly improved mobile and wi-fi connectivity, so that passengers can make the most of their travel time and
  • communities close to the railway can connect more easily
So when will we start introducing ETCS Level 2 on trains – passenger and freight – maybe using the Siemens’ Trainguard Level 2, Baseline 3 system.
In a rail network where passenger and freight services use the same tracks much, if not most of the time, then they will all need to be fitted from new, and retrofitted to older stock and locomotives.
Here’s one but at least.  On a previous occasion, it was announced that: “Freight trains in Britain to be upgraded with delay-busting digital technology in multi-million pound deal”  This according to Network Rail has already started, although retrofitting the fleet will not start for another 3 years:
“The design, testing and approvals stage for each class of vehicle starts now and work to retrofit the entire freight fleet will begin in 2022 and continue through to Control Period 7 (CP7, 2024-2029).”
All of this is true, and was being planned and partially implemented more than 20 years ago, so why the delays.  Maybe it’s just down to education, since as the “Digital Railway” website advertises:
“The European Rail Traffic Management System – ERTMS Education Day is open to rail operators and aims to deliver an overview of ERTMS and its place as part of the wider Digital Railway programme. It includes the rationale behind ERTMS, how the system operates and changes to on-train and lineside infrastructure.”
ERTMS Education Days are operated jointly by the Rail Delivery Group (RDG) and Network Rail.  I get the involvement of Network Rail, but why the RDG?  Is that just a collective name for various passenger and freight operating companies?  Or is it to fill a gap that was once provided by the Railway Clearing House (RCH) – back in steam days.
Ah well, at least some progress with modern signalling technology seems to be coming along – what a pity that it has taken so long to begin to catch up with other European countries.

-oOo-

Blackpool Lights Up – Finally

Standard

The 19 week programme to electrify the line from Preston to Blackpool North has – it seems – finally been completed, and on 16th April, the new service is now planned to start.  The programme was extended by a 3 weeks – and according to Network Rail, the major cause of the delay was the extreme bad weather in March.

PROJECT UPDATE: Blackpool North line to reopen on Monday 16 April

So, the project has overrun by 16% – but at least it is now finished.  Services to Blackpool stopped on 11th November and were due to restart on the 26th March – in good time for the start of the Easter holidays and the tourist season.

When the delay was announced the MP for Blackpool South was incensed and took the matter up with Norther Rail (the franchisee), and of course in Parliament.  The local paper carried a story about the delay:

‘Damaging’ rail delay will impact on tourism, says MP

However, Network Rail has completed:

  • Rebuilding 11 bridges
  • Remodelling 11 station platforms
  • Replacing 11km of track
  • Upgrading drainage
  • Installing a completely new signalling system, operated entirely from the Manchester ROC

Alongside the changes at Blackpool North and Kirkham & Wesham stations, Blackpool train care depot to support the roll out of new Class 331 trains later in 2018.

In the meantime Class 319 units will be relocated from Southern England – good to recycle.  But at least one observer has noted that whilst Transpennine run electrified services into Manchester Airport, currently it seems Northern Rail are not planning for this.

Whilst Network Rail are to be congratulated on completing the job – it’s still ‘wait and see’ to find out how the ‘Great Northern Rail Project’ fulfils its declared intentions.

 

Now That’s What I Call A Digital Railway

Standard

This video on signalling has just been published by the UIC:

And, as they say:

Signalling is an essential cornerstone of the railway system

Bit different to this:

RPBRLY-1

Or even this:

RPBRLY-2

And even in the UK there is ‘new kid on the block’ (pardon the pun!), it is the “digital railway” – on the official website, this is what they say that this new technology for train control and signalling will provide:

 

“Digital Railway aims to deliver the benefits of digital signalling and train control more quickly than current plans, deploying proven technology in a way that maximises economic benefit to the UK.”

-oOo-

Network Rail’s Upgrade Plan

Standard

According to their latest Tweets and New Releases, Network Rail’s “Railway Upgrade Plan” is the biggest investment and engineering project/programme of projects since Victorian times.  Now I know that’s a bit of a stretch, but…

https://fast.wistia.com/embed/iframe/bzvre7n5h8

The video is imaginative and entertaining.

According to Network Rail:

In the last 20 years the number of people travelling on the rail network has doubled, and the rail network, our stations and our platforms are dealing with more passengers than they were ever designed for.

But our investment plan is now entering its final phases and better, more frequent, faster journeys for hundreds of thousands of people are now months away for some, as the benefits start to come to fruition.

Millions of passenger journeys will be transformed in the months ahead and through to 2021 as more and more new services come on-stream

There are 4 “Mega projects”, the Edinburgh to Glasgow Improvement Programme, Crossrail, Derby Resignalling and the Great North Rail Project.  On top of this there are the “National Projects” – East-West Rail, Midland Mainline and Trans Pennine.

Scotland-EGIP-Queen-Street-tunnel-1035x545I get the £742 million for Edinburgh to Glasgow (outstanding since about 1981), and £200 million for Derby resignalling, and the massive Crossrail project is a given.  But, the Great North Rail Project is really just putting in place work that should have been done years ago, especially in view of the growth in passenger numbers, and the need to replace outdated and life expired technology.

Should the “Railway Upgrade Plan” for CP6 and beyond perhaps, be considered alongside the 1950s “Modernisation and Re-Equipment Programme”?

The latest news has some really interesting drill down options too, and worth a read, but I’m still unsure about the comparisons with 100 years and more ago.

Our Railway Upgrade Plan

-oOo-

 

 

 

 

 

The Great North Rail Project

Standard

As part of Network Rail’s £1 billion, 25-year “Railway Upgrade Plan” there are 7 projects that form the  “Great North Rail Project” sub-project which is intended to be complete by 2022 – only 4 years from now.  They include:

  • Liverpool City Region upgrade
  • Manchester to Preston improvements
  • Preston to Blackpool North
  • Transpennine Route upgrade
  • West Yorkshire signalling upgrade
  • Ordsall Chord
  • Calder Valley improvements

These seven projects are highlighted as the infrastructure improvements in the north of England.  Fair enough, Network Rail doing infrastructure work – but these projects seem to suggest Network Rail may be providing new trains – in particular there is a reference to those trains as part of the “Railway Upgrade Plan”.

The key benefits include longer, faster, more frequent trains; a better, more reliable infrastructure; and better facilities for passengers, especially at stations.

To be fair, and maybe I am being picky but isn’t it the job of the rolling stock leasing companies to buy and offer the new trains to the train operating companies – Transpennine, Northern Rail, etc. – not Network Rail.  Or perhaps since the physical infrastructure is being upgraded, is this going to be a first step towards re-nationalisation?

However, amongst the key projects of this grand plan, electrification is being progressed – yet not in the North.  The new “Azuma” trains have already encountered a problem, since the East Coast Main Line franchise is soon to be terminated, so they may not enter service at all, or be delayed, or under a publicly owned railway.  Similarly, Network Rail indicate that HS2 is one of their key projects – but I thought this was another privately funded scheme.

So where are we today?  There is still a lot of infrastructure work to be completed before Blackpool can be reached by a new electric train service, and Liverpool Lime Street is being closed in the summer for a couple of months, and the Chorley “Flying Arches” appear to be uplifted.

Here are a few snaps of work in progress in the North West:

 

 


Not so High Speed Northern Rail

Standard

Last month (November), the Government published its vision paper on rail, entitled Connecting people: a strategic vision for rail”, extolling the virtues of the latest UK plans for ‘modernising” the rail infrastructure and services. It sets great store by the increased investment already made, against the backdrop of ever increasing passenger numbers, much of which is accurate.

At the same time it makes some bizarre statements about cuts in journey times of 15 minutes between Liverpool and Manchester that are simply not borne out by facts. Here’s what it says on page 21 of the published document:

  • “2.18  This investment in rail networks in the North of England has already delivered improvements, with the fastest journey between Liverpool and Manchester cut by 15 minutes, new direct services between Manchester Airport and Glasgow, and Manchester Victoria station upgraded. 
”

It carefully avoids any comparison with a figure for earlier years, so we are left to wonder if they mean the journey is 15 minutes quiker compared with 1947, 1957, or 1977.

However, comparing this claim between the timings for 2017 with those of the 1972 timetable – 45 years ago! – the fastest journey time is only 6 minutes quicker, and in 1972, there was still a lot of steam age legacy infrastructure and systems in place.

This is 2017

Liverpool to Manchester 2017

Fastest Journey Liverpool Lime Street to Manchester (Piccadilly / Victoria)

 

1972 - 2017 TimingsThe fastest services in 1972 were operated as ‘Inter-City’, with this example of a weekday service leaving Lime Street at 08:35, and arriving at Piccadilly 51 minutes later. Today’s service has only 1 more stop, at Wavertree Technology Park, a new station, and yet only manages a 6 minute reduction in journey time.

Still it is quicker, and yes, I am being picky!

This is 1972

Overall, the ideas suggested include work that has already been done, and work that might get completed. With the cancellation of electrification in the north earlier this year, in favour of Crossrail 2, I’m not holding my breath.

Investment in new trains as well as new technology is and has been long overdue, but to keep referencing HS2 in this ‘vision’ paper does not cut the mustard if the DfT want to demonstrate a commitment to rail services. Changes to franchising are perhaps just adding ever more complexity and ‘red tape’ to a privatisation scheme that has not offered a major performance – both operationally and economically – improvement to the UK’s network. The UK is still, after 25+ years of a ‘privatised railway’, still subsidising train operating companies.

Ah well, let’s see what happens next.

-oOo-

 

Closing the Blackpool Line

Standard

Today, 10th November 2017, it has been announced that the line from Preston to Blackpool is to be closed for 19 weeks, to carryout ‘electrification works’, and a replacement bus service will operate instead.  But not all of the line is to be electrified, since only the ‘northern’ route via Poulton will receive the overall benefit, whilst the coastal line through Lytham, St Annes and Blackpool South will remain non-electrified – wonder how that will affect the choice of multiple units to be used.

I imagine this must be because either Network Rail don’t have the necessary technical and management skills, or sufficient resources and experience to electrify the line whilst maintaining a train service.  However did we manage to electrify the West and East Coast main lines in the 1960s and 1980s/90s and still run a train service.

Between 11th November 2017 and 28th January 2018, no trains will run to Blackpool, Lytham, and all points in between at all.  The route to Blackpool South will re-open at the end of January, but the line from Kirkham to Blackpool North will stay closed until 25th March.

The line to Blackpool North from Preston remains a double track route, whilst the ‘coastal route’ between Kirkham, Lytham, St Annes and Blackpool South was reduced to single track many years ago.

However, I have a question – why would Network Rail and the DfT consider that it must close the whole of the double track line to Blackpool??

The work is being carried out as part of the “Great North Rail Project” which, according to Network Rail will “..deliver modern, faster, more frequent and more comfortable train services across one of the largest rail networks in the country.”  On top of this, services will be more reliable, greener and have more seats, on new trains.

Surely, the reliability and comfort/efficiency of train operations will be down to the capability of the train operating companies, and not just the infrastructure manager alone.  I appreciate that resignalling will create, along with electrification a much improved rail line, but it’s not just NetworkRail’s job to see that it really happens.

For the moment – and until the end of March 2018, passengers will have to manage their journeys differently – has the economic risk and impact of closing the line for almost 5 months been considered?  The single line section from Kirkham around the coast to Blackpool South also includes Squires Gate Station – handy for access to Blackpool Airport – would there be a risk to air passengers?

Interestingly, Blackpool North was earmarked for closure under the 1963 Beeching proposals, whilst the line to Fleetwood was closed, was closed to passenger traffic, but retained in part.  The Fylde Coast lines were still generating considerable passenger traffic – albeit seasonal – 50 years ago, and between 2009 and 2012, the remaining stations in Blackpool saw year on year increases, and now at around 2 million passengers annually.

The electrification is clearly both welcome and needed – just a pity the line is to close for 5 months.

Further reading:

https://www.northernrailway.co.uk/news/improvements/1435-preston-to-blackpool-11-november-2017-25-march-2018

http://www.lancashire.gov.uk/lancashire-insight/transport/railway-stations-usage.aspx

https://www.networkrail.co.uk/running-the-railway/our-routes/lnw/north-west-electrification/preston-blackpool-north/

-oOo-

Crossrail 2 Hits the Buffers?

Standard

In a press release today, the Chartered Institute of Logistics and Transport (CILT) expressed concern that Crossrail2 was not mentioned in this week’s Queen’s Speech, although commitment to HS2 was retained.

Crossrail 2 is targeted at relieving congestion on commuter routes into and across London, but it will be some years before this project is completed.  Crossrail 1, or “The Elizabeth Line” is not due to open for services until 2018/19.

“We are, however, concerned that there was no mention of Crossrail 2 in the Speech. This scheme is vital not only to keep London moving and to support its further economic and social development, but also as a key element of the national transport infrastructure which serves the entire national economy. As Britain looks to plan for a post-Brexit future, investment in mobility is of even greater importance. Therefore, CILT calls on the Government to make a clear commitment to the future of the Crossrail 2 project.”

The line itself – if it is ever built – follows the route illustrated below:

Crossrail 2

The core line from Tottenham Hale and Seven Sisters through St Pancras, Euston, Victoria and down to Clapham Junction.  I suspect that the ‘branches’ will never get built, and now, maybe even doubts about this ‘core’ section.

Maybe the CILT aren’t far wrong as Daniel Parker-Klein, Head of Policy, CILT said:

“It is imperative that Government commits to support the development of Crossrail 2.  This scheme is essential for not only London’s future but for the whole of the UK.  There is little time for delay – a hybrid bill must be submitted by 2020.  Without it, the benefits of HS2 may not be realised, the movement of goods and people will be constrained and the UK’s economy will be less resilient to meet the demands of an uncertain future.”

What a good job we have a competent and wide ranging transport strategy in the UK as leave the EU.

-oOo-